This is a migrated thread and some comments may be shown as answers.

update recurring scheduled run

5 Answers 77 Views
General Discussions
This is a migrated thread and some comments may be shown as answers.
Doga Ercan
Top achievements
Rank 1
Doga Ercan asked on 11 May 2012, 03:45 PM
Hi,

I have recurring scheduled run in execution server. I could see waiting test runs (in yellow) in my local machine, but now they are disappeared. In case of updating them, i could just click on them and make my update. Now I cannot see those waiting one, therefore cannot update them. I tried reload from server but it did not reload all of them. 

Do you have any idea why i cannot see waiting runs and how i can update those if i cannot see them?

Thanks

Ercan

5 Answers, 1 is accepted

Sort by
0
Ivaylo
Telerik team
answered on 14 May 2012, 04:16 PM
Hello Doga,

I have investigated the issue you are experiencing and it turned out it's a bug. I've managed to log this bug and you can keep track using this public URL. Regarding reload from server it should work but it is kind of tricky, please go to the date when you scheduled the test run and then click Reload from Server button, then it should reload your scheduled runs.
Here is an example, I have reproduced this behavior and scheduled test runs from today which are not present in the calendar. Another known issue with the calendar is that it lands on the date with latest results available which on my testing project is 21st of March. When I push Reload from Server when I am on 21st of March nothing happens, when I navigate the calendar to 14th of May (the date I scheduled the test) and push Reload from Server, the scheduled runs appear. I've created for you a short video example on this workaround.

Hope this will work for you.

Thank you for your understanding and patience.

Kind regards,
Ivaylo
the Telerik team
Quickly become an expert in Test Studio, check out our new training sessions!
Test Studio Trainings
0
Benjamin
Top achievements
Rank 1
answered on 23 Jul 2012, 05:13 PM
The Public Issue record states the issue is fixed and stated it was designed that way on purpose. However, it has not been resolved. Recurring scheduled runs do not refresh as stated previously. Instead you still need to find the date the run was originally scheduled for it to be displayed. Could this issue be reopened?
0
Ivaylo
Telerik team
answered on 25 Jul 2012, 11:59 AM
Hello Benjamin,

I have raised this issue again. You can find the bug at this public URL.

Regards,
Ivaylo
the Telerik team
Quickly become an expert in Test Studio, check out our new training sessions!
Test Studio Trainings
0
Doga Ercan
Top achievements
Rank 1
answered on 06 Nov 2012, 10:55 AM
Hi,

In PITS link above, it says: "Telerik: The issue is resolved and the fix will be available with the next internal build scheduled for the second half of October."

Can you please give information about which build version includes this fix?

Thanks

Ercan
0
Ivaylo
Telerik team
answered on 06 Nov 2012, 01:57 PM
Hello Doga Ercan,

This issue should be solved in our latest internal build (version 2012.2.1022) available for download from the following link.
Please give it a try and if you still have any further problems please let me know.

All the best,
Ivaylo
the Telerik team
Are you enjoying Test Studio? We’d appreciate your vote in the ATI automation awards.
Vote now
Tags
General Discussions
Asked by
Doga Ercan
Top achievements
Rank 1
Answers by
Ivaylo
Telerik team
Benjamin
Top achievements
Rank 1
Doga Ercan
Top achievements
Rank 1
Share this question
or